The evaluation and selection of projects which are most likely to maximise shareholders' wealth.
Periodic yield is a rate of return - or cost of borrowing - expressed as the proportion by which the amount at the end of the period exceeds the amount at the start.  


''Also known as Project appraisal.''


====Example 1====


GBP 1 million is borrowed or invested.
== See also ==
 
* [[Project appraisal]]
GBP 1.03 million is repayable at the end of the period.
* [[Analysis paralysis]]
 
 
The periodic yield (r) is:
 
r = (End amount / start amount) - 1
 
Which can also be expressed as:
 
r = (End / Start) - 1
 
''or''
 
r = <math>\frac{End}{Start}</math> - 1
 
 
= <math>\frac{1.03}{1}</math> - 1
 
= 0.03
 
= '''3%'''
 
 
====Example 2====
 
GBP  0.97 million is borrowed or invested.
 
GBP 1.00 million is repayable at the end of the period.
 
 
The periodic yield (r) is:
 
r = <math>\frac{End}{Start}</math> - 1
 
 
= <math>\frac{1.00}{0.97}</math> - 1
 
= 0.030928
 
= '''3.0928%'''
 
 
''Check:''
 
Amount at end = 0.97 x 1.030928 = 1.00, as expected.
 
 
====Example 3====
 
GBP  0.97 million is invested.
 
The periodic yield is 3.0928%.
 
Calculate the amount repayable at the end of the period.
 
 
'''''Solution'''''
 
The periodic yield (r) is defined as:
 
r = <math>\frac{End}{Start}</math> - 1
 
 
''Rearranging this relationship:''
 
1 + r = <math>\frac{End}{Start}</math>
 
 
End = Start x (1 + r)
 
 
''Substituting the given information into this relationship:''
 
End = GBP 0.97m x (1 + 0.030928)
 
= '''GBP 1.00m'''
 
 
====Example 4====
 
An investment will pay out a single amount of GBP 1.00m at its final maturity after one period.
 
The periodic yield is 3.0928%.
 
Calculate the amount invested at the start of the period.
 
 
'''''Solution'''''
 
As before, the periodic yield (r) is defined as:
 
r = <math>\frac{End}{Start}</math> - 1
 
 
''Rearranging this relationship:''
 
1 + r = <math>\frac{End}{Start}</math>
 
 
Start = <math>\frac{End}{(1 + r)}</math>
 
 
''Substitute the given data into this relationship:''
 
Start = <math>\frac{1.00}{(1  +  0.030928)}</math>
 
 
= '''GBP 0.97m'''
 
 
''Check:''
 
Amount at start = 0.97 x 1.030928 = 1.00, as expected.
 
 
====Effective annual rate====
 
The periodic yield (r) is related to the [[effective annual rate]] (EAR), and each can be calculated from the other.
 
 
==See also==
 
*[[Effective annual rate]]
*[[Discount rate]]
*[[Nominal annual rate]]
*[[Periodic discount rate]]
*[[Yield]]

Revision as of 09:46, 2 May 2016

The evaluation and selection of projects which are most likely to maximise shareholders' wealth.

Also known as Project appraisal.


See also