Sunk costs

From ACT Wiki
Revision as of 14:46, 31 March 2020 by imported>Doug Williamson (Layout.)
Jump to navigationJump to search

Project appraisal.

Expenditure which has already taken place, or to which an organisation is already irrevocably committed, are sunk costs.

Sunk costs are irrelevant to project appraisal: "Sunk costs don't count."


A common mistake in project appraisal and analysis is the inclusion - in error - of sunk costs in the analysis.


See also