Present value

From ACT Wiki
Revision as of 15:42, 30 November 2015 by imported>Doug Williamson (Generalise first example from years to periods.)
Jump to navigationJump to search

(PV).

Today’s fair value of a future cash flow, calculated by discounting the future cash flow at the appropriately risk adjusted current market cost of capital.


Example 1

If $110m is receivable one period from now, and the appropriate periodic cost of capital (r) for this level of risk is 10%,

the Present value is:

PV = $110m x 1.10-1

= $100m.


And more generally:

PV = Future value x Discount factor(DF)

Where:

DF = ( 1 + r )-n

r = cost of capital per period; and
n = number of periods


Example 2

If $10m is receivable one year from now, and the cost of capital (r) is 6% per year,

the Present value is:

PV = $10m x 1.06-1

= $9.43m.


Example 3

Now let's change the timing from Example 2, leaving everything else the same as before.

If exactly the same amount of $10m is receivable, but later, namely two years from now,

and the cost of capital (r) is still 6% per year,

the Present value falls to:

PV = $10m x 1.06-2

= $8.90m.


The longer the time lag before we receive our money, the less valuable the promise is today.

This is reflected in the lower Present value for the two years maturity cash flow of $8.90m, compared with $9.43m Present value for the cash flow receivable after only one year's delay.