Present value: Difference between revisions
imported>Doug Williamson m (Link with qualifications page.) |
imported>Doug Williamson (Updated entry. Source ACT Glossary of terms) |
||
Line 4: | Line 4: | ||
For example, if $110m is receivable one year from now, and the cost of capital (r) is 10% per year, the Present value is: | For example, if $110m is receivable one year from now, and the appropriate cost of capital for this level of risk (r) is 10% per year, the Present value is: | ||
PV = $110m x 1.1<sup>-1</sup> | PV = $110m x 1.1<sup>-1</sup> | ||
Line 25: | Line 25: | ||
===Examples=== | ===Examples=== | ||
For example, if $10m is receivable one year from now, and the cost of capital (r) is 6% per year, the Present value is: | For example, if $10m is receivable one year from now, and the cost of capital (r) is 6% per year, | ||
the Present value is: | |||
PV = $10m x 1.06<sup>-1</sup> | PV = $10m x 1.06<sup>-1</sup> | ||
Line 33: | Line 35: | ||
Now changing the timing in this example, if exactly the same amount of $10m is receivable but later, namely two years from now, and the cost of capital (r) is still 6% per year, the Present value falls to: | Now changing the timing in this example, | ||
if exactly the same amount of $10m is receivable but later, namely two years from now, | |||
and the cost of capital (r) is still 6% per year, the Present value falls to: | |||
PV = $10m x 1.06<sup>-2</sup> | PV = $10m x 1.06<sup>-2</sup> |
Revision as of 10:51, 26 November 2014
(PV).
Today’s fair value of a future cash flow, calculated by discounting the future cash flow at the appropriately risk adjusted current market cost of capital.
For example, if $110m is receivable one year from now, and the appropriate cost of capital for this level of risk (r) is 10% per year, the Present value is:
PV = $110m x 1.1-1
= $100m.
And more generally:
PV = Future value x Discount factor (DF)
Where:
DF = (1+r)-n
- r = cost of capital per period; and
- n = number of periods
Examples
For example, if $10m is receivable one year from now, and the cost of capital (r) is 6% per year,
the Present value is:
PV = $10m x 1.06-1
= $9.43m.
Now changing the timing in this example,
if exactly the same amount of $10m is receivable but later, namely two years from now,
and the cost of capital (r) is still 6% per year, the Present value falls to:
PV = $10m x 1.06-2
= $8.90m.
The longer the time lag before we receive our money, the less valuable the promise is today.
This is reflected in the lower Present value for the two years maturity cash flow of $8.90m, compared with $9.43m Present value for the cash flow receivable after only one year's delay.